Waga Energy signs a new agreement in the United States to produce up to 120 GWh of biomethane per year
Waga Energy has entered into an agreement to build a biogas upgrading unit in Modoc, Indiana, with two companies of the family-owned group The Balkema Companies.
This is the second collaboration between the two groups, following the commissioning of a first unit in August 2026 at the Decatur Hills site in Greensburg. The new equipment is scheduled to enter service in early 2028.
A unit in Modoc to replace the upgrader at Best Way Disposal
The agreement was signed with Randolph Farms Landfill and Best Way Disposal, subsidiaries of The Balkema Companies, a group active in waste management, construction and aggregates. The unit will recover the gas spontaneously emitted by the waste buried at the Randolph Farms storage site, which the group has operated since 1986.
The new equipment will replace the upgrader that currently supplies the Best Way Disposal refueling station installed on site. The biomethane produced may be injected into the natural gas transmission network and marketed, notably as a fuel for transport.
Financing provided by Waga Energy, with shared revenues
Under the terms of the agreement, Waga Energy will finance and build the unit, own it and operate it for at least 20 years. Randolph Farms will manage the biogas collection network and contribute to the civil engineering work, with the two partners sharing the revenues from the sale of the biomethane.
Waga Energy is thus providing the financing for the equipment, and its remuneration depends on the sales shared with the owner of the site. Equipped with Wagabox technology, which uses cryogenics, the unit will be able to process up to 3,200 m³/h of raw biogas and produce up to 120 GWh of biomethane per year at full capacity.
A fleet of 38 units in operation and 22 under construction
Replacing fossil natural gas, this biomethane will avoid the emission of approximately 31,700 tonnes of CO₂ equivalent per year, according to an estimate by the company based on the methodology of the United States Environmental Protection Agency.
To date, Waga Energy operates 38 units in France, Spain, Canada and the United States, for an installed capacity of more than 2.1 TWh per year, and has 22 units under construction worldwide.
Guénaël Prince, Chief Executive Officer of Waga Energy Inc., stated: “With this second facility, we are strengthening our presence in Indiana, where we are creating a true renewable energy hub.” Jessica Routley, Chief Executive Officer of The Balkema Companies, indicated that the project makes it possible to recover biogas “rather than letting it go to waste.”